Skip to content
Sumly

Deadline Calculator

Add working days, weeks or months to a kickoff date.

In

Out

Deadline

Mon, Nov 23, 2026

21 calendar days after kickoff

KickoffMon, Nov 2, 2026
Deadline weekdayMonday
Calendar span21 days
Working days in span15
Duration used15 working days
Working days skip weekends; the start day itself is not counted — 15 working days from a Monday lands on the Monday three weeks later.

How the Deadline calculation works

Working-day mode advances Monday through Friday only, so 15 working days from a Monday lands on the Monday three weeks later — and the start day itself is never counted.

Calendar-day, week and month modes include weekends. Months clamp to the end of shorter months: January 31 plus one month is February 28, not a date that does not exist.

The result panel shows the deadline's weekday (nobody wants a Friday-4pm delivery), the calendar span, and how many of those days were working days.

Worked example

Kick off Monday, November 2 2026 with 15 working days and the deadline lands on Monday, November 23 — a 21-calendar-day span containing exactly 15 working days. Switch to calendar days and 15 lands earlier, on Tuesday, November 17.

The tool above opens with these numbers. Change them to run your own scenario, or press Reset to come back to this example.

Frequently asked questions

Count real working days between two dates — weekends and holidays out.

A 25/5 focus timer that counts your pomodoros as you bank them.

What a recurring meeting really costs — per session and per year.

Turn estimated hours into a defensible project price.

One time in one zone, translated to twelve cities at once.

Calculate engineering sprint capacity and recommended story point commitments.

  • deadline
  • dates
  • planning
  • working days
  • productivity