Project Cost Calculator

Turn estimated hours into a defensible project price.

In

All roles combined

Software, contractors, hardware

15–25% is typical

Out

Total project cost

$40,135

320 h × $95/hr + fixed + contingency

Labour cost$30,400
Fixed costs$4,500
Contingency (15%)$5,235
Burn per week$3,345
Suggested quote at 30% margin$57,336
Profit on that quote$17,201
Quote with margin, not markup: 30% margin on cost means 0% on price. The pricing calculator shows why.

How the Project Cost calculation works

Labour = estimated hours × blended rate across all roles. Fixed costs — software, contractors, hardware — ride on top, and contingency applies to the sum, because overruns burn fixed costs too.

Burn per week divides total cost by planned duration: your weekly cash commitment, useful for spotting a 12-week project that quietly costs more per week than it bills.

The suggested quote divides cost by (1 − margin): a 30% margin means 30% of the final price is profit — which is a 43% markup on cost, and the two numbers get confused constantly.

Worked example

320 hours at $95 is $30,400 of labour; add $4,500 fixed and 15% contingency ($5,235) for a $40,135 total. That burns $3,345 a week across 12 weeks, and the 30% margin quote prices the job at $57,336 — $17,201 of profit.

The tool above opens with these numbers. Change them to run your own scenario, or press Reset to come back to this example.

Frequently asked questions

What a recurring meeting really costs — per session and per year.

Count real working days between two dates — weekends and holidays out.

A 25/5 focus timer that counts your pomodoros as you bank them.

Add working days, weeks or months to a kickoff date.

One time in one zone, translated to twelve cities at once.

Calculate engineering sprint capacity and recommended story point commitments.

  • project
  • cost
  • budget
  • quote
  • productivity